All projects
Riverside Deck Build
New timber deck build and staining for a riverside residential property, including framing and finish work.
Active
12 Riverside Dr2024-05-27 — 2024-06-14
Crew on this job
2
Hours this week
52
Labor cost this week
$1,800
Weekly task log
Enter or edit each crew member's task and hours for each day. A day counts as worked once hours are logged.
| Crew member | Mon 06-03 | Tue 06-04 | Wed 06-05 | Thu 06-06 | Fri 06-07 | Hours | Cost |
|---|---|---|---|---|---|---|---|
| Kevin Ruiz Carpenter $270/day | hrs | hrs | hrs | hrs | hrs | 30 | $1,080 4/5 days |
| Liam O'Brien Labourer $240/day | hrs | hrs | hrs | hrs | hrs | 22 | $720 3/5 days |
Weekly cost summary
Days worked × daily rate for each crew member on Riverside Deck Build.
Kevin Ruiz4 days × $270$1,080
Liam O'Brien3 days × $240$720
Total this week$1,800